3373-R3_ML&P_TownOfBuxton_Web

Code Enforcement Report

The number of new homes dropped slightly from last year, with most being stick built. Norman Berube Builders completed the 10 lot subdivision at Crossing Brook in early fall. The manufactured /mobile homes mostly replaced existing dwellings so there was no real change. The accessory structures, such as garages, sheds, decks and pools remained about the same. Alterations and additions were about 30% less, suggesting owners are waiting to see if loans are accommodating enough to take on a project. The overall number of 83 plumbing/septic permits was close to the last two years, but therewas a significant shift in the Septic Wastewater Disposal System permits. Of the 49 SWDS, 28 replacement systems were 60%of the total number installed. This is twice as many as those installed last year, indicating older systems are reaching their expiration date. These are living, active systems that need care in what goes into it and tanks that should be pumped at appropriate times to extend their life to its expected service. Of the new homes being built this year, there have been new materials and assemblies to work with, somewhat different than the traditional stick built. We’ve seen Styrofoam panels hinged together with plastic connectors that when straightened create the foundation forms into which the concrete is poured. Another has been just the opposite where expanded polystyrene foam is sandwiched between exterior ZIP board and OSB for exterior roof and walls. Heated concrete floors used mesh and ties to hold the winding loops in place. Now there is a Styrofoam panel with an array of plastic knobs around which the plastic piping can be easily snapped in and held in place for the pouring of the floor. The ease of installation of these products helps reduce costs as well as providing consistency in product and use. Homes and septic systems need to be maintained in order for them to continue providing the shelter and disposal we need. But continued use without care will eventually be a problem for the owner as well as the neighbors. Rural Development and York County Community Action are two agencies that may provide assistance in replacing either or both. In working with these two agencies, two septic systems were replaced and a new mobile home, pad and septic system was installed. A reasonable payment plan allows the owner to continue living there while making modest payments.

Category

2009 2010 2011 2012 2013 2014

Stick Build Homes

14 10

13

8 2 1

15

19

20

Manufactured/Mobile Homes

8 1

9

5 2 9

3 0

Modular Homes

1

Garages

14 31 79

11 28 54

21 40 53

13 35 60

11 23 57

Alterations & Additions

34 55

Sheds, Decks, Pools & Misc.

Total Building Permits SSWS (septic system)

149

115

125 132

124

114

45 40

36 32

31 21

40 38

41 40

49 34

Internal Plumbing

Total Permits

234

183

177 210

205

197

Submitted by:

Fred Farnham, Code Enforcement Officer

17

Made with FlippingBook - professional solution for displaying marketing and sales documents online